What a CRMA Strategic Project designation means
The Critical Raw Materials Act (Regulation (EU) 2024/1252) sets EU benchmarks for 2030: at least 10% of annual consumption of strategic raw materials extracted in the EU, 40% processed in the EU, 25% recycled in the EU, and no more than 65% of any strategic raw material sourced from a single third country. Strategic Projects are the Commission's chosen instruments for reaching those targets.
The Commission adopted its first list of EU projects on 25 March 2025 and a list of projects in third countries on 4 June 2025. A second EU list of 46 projects followed in October 2026, bringing the total to around 106.
What promoters gain
- Faster permits. Permit-granting for extraction projects is capped at 27 months and for processing and recycling projects at 15 months, and projects are treated as being of overriding public interest.
- Financing support. The Commission, the EIB and Member States coordinate access to finance through the Critical Raw Materials Board; designation is a signal to lenders and offtakers.
- Offtake matchmaking. Strategic Projects are natural candidates for the EU's joint purchasing and offtake platforms.
Value-chain stages
| Stage | Typical projects |
|---|---|
| Extraction | Hard-rock and claystone lithium, nickel-cobalt, tungsten, copper, bauxite |
| Processing | Lithium hydroxide converters, synthetic and natural graphite anodes, cobalt refining, rare earth separation |
| Recycling | Black-mass hydrometallurgy, magnet and PGM recycling |
| Substitution | Technologies that reduce demand for a critical material |
Who uses the list
Battery and magnet makers look for European feedstock; EPC contractors, equipment vendors and reagent suppliers look for projects with accelerated permits; banks, export-credit agencies and offtakers look for de-risked pipelines. Many projects are promoted by a local subsidiary, so the promoter named in the decision may differ from the listed parent company.
Designation does not guarantee that a project will be built; it speeds permitting and improves access to finance, but each project still needs its own permits and funding.