Who is queuing battery storage on the US grid
Every utility-scale battery project in a US organised market must enter its ISO or RTO's generator interconnection queue before it can be studied, sign an interconnection agreement and connect. Storage has become one of the largest technology categories in these queues, and the queues are the earliest public record of who is developing which project, where and at what size.
What the queues disclose
Each ISO/RTO publishes its own queue format and level of detail. NYISO's spreadsheet, for example, names the developer or interconnection customer for every request and separates serial-queue projects, Cluster 2024 projects, withdrawn requests and in-service projects, with storage capability in MWh. Other markets publish queue IDs, fuel type, MW, county and status, but disclose the customer name to differing degrees, so developer names sometimes have to be matched from study reports and interconnection agreements.
Reading a queue entry
- The customer is usually a project LLC. Many entries, such as numbered series companies, belong to the same parent developer.
- Most requests never connect. Historically a large majority of projects entering US queues withdraw, so status and study phase matter more than total MW.
- Cluster reforms. Following FERC Order No. 2023, ISOs moved from first-come serial queues to cluster studies with higher deposits and readiness requirements, which thins speculative requests.
Who uses the developer list
Battery integrators and cell suppliers, EPC contractors, inverter and transformer makers, tax-equity and debt providers, land agents and offtakers use queue data to find developers before procurement. Capacity (MW) and energy (MWh) together indicate duration — 4-hour systems dominate recent NYISO cluster entries.