Accredited renewable power stations: the supply side of Australian PPAs
Under the Renewable Energy (Electricity) Act 2000, a power station must be accredited by the Clean Energy Regulator (CER) before it can create Large-scale Generation Certificates (LGCs). Each LGC represents one megawatt-hour of eligible renewable electricity. Because corporate buyers in Australia usually purchase LGCs bundled with electricity in a power purchase agreement, the CER's accreditation records are the authoritative list of generators that can actually deliver renewable PPAs.
What the CER publishes
| Dataset | What it covers |
|---|---|
| Accredited power stations | Stations approved in the year, with accreditation code, state, postcode, installed capacity, fuel source and dates |
| Committed projects | Projects with a final investment decision or financial commitment |
| Probable projects | Projects with significant progress but not yet committed |
| Total LGCs and capacity | Aggregate certificates and capacity of accredited stations |
Reading the records
- Accreditation codes start with a fuel-related prefix, for example WD for wind and SRP for solar.
- Station names are free text chosen by the applicant, so the owning company has to be matched separately; some names include the owner or project company, as with Broadsound Solar Farm Pty Ltd.
- The list mixes scales. Utility-scale wind and solar farms of several hundred MW sit next to rooftop systems of a few hundred kilowatts at warehouses, aged-care homes and stadiums.
Why PPA buyers start here
A newly accredited station has certificates to sell and often uncontracted output. Large stations accredited in 2026 include wind farms in Victoria and Queensland above 250 MW and solar farms above 300 MW. Buyers comparing offers can check that a counterparty's station is accredited, its fuel source and its capacity before negotiating volume, tenor and LGC delivery.