How the UK picks its CfD winners
Contracts for Difference (CfDs) are the UK's main support scheme for new low-carbon generation. Developers bid a strike price in a sealed-bid auction; winners sign a 15- to 20-year contract with the Low Carbon Contracts Company (LCCC), which pays the difference when the market reference price is below the strike price and receives it back when the market is above. Rounds are run by the Department for Energy Security and Net Zero (DESNZ), with eligibility and auction administration by National Energy System Operator.
Pots and technologies
| Pot | Technologies |
|---|---|
| Pot 1 — established | Solar PV, onshore wind, energy from waste, hydro, landfill and sewage gas |
| Pot 2 — less established | Tidal stream, geothermal, advanced conversion technologies (ring-fenced minimums) |
| Pot 3 — offshore wind | Fixed-bottom offshore wind |
| Pot 4 — floating offshore wind | Floating offshore wind |
Allocation Round 7
AR7 was split: offshore wind results (Pots 3 and 4) were published in January 2026, with solar, onshore wind and other technologies following in AR7a. Fixed-bottom offshore wind cleared mostly at £91.20/MWh in 2024 prices, with Berwick Bank Phase B lower at £89.49, while floating projects such as Erebus and Pentland cleared at £216.49. Many winning units are special-purpose companies — for example separate East and West companies for Norfolk Vanguard and Dogger Bank South — so the ultimate sponsor often differs from the applicant name.
Why the winners list is a supply-chain target list
- Delivery deadlines. Each unit has a target commissioning window (for AR7 offshore, mostly 2028/29 to 2030/31), so turbine, foundation, cable, vessel and port contracts must be placed years earlier.
- Phased projects. Projects with several phases have staggered procurement.
- Repeat bidders. Developers that win in one round usually return with further phases.
A CfD can be terminated if milestone requirements are not met, so not every winning project reaches commercial operation.